POWER PLANT RELOCATION PROJECT (10 MW)/ TURKEY-2015:

All main machine groups, electronic and mechanical equipment were disassembled by 11 Industrial and they were transported and reassembled to the new jobsite.

PROJECT OF REMOVAL OF DAMAGED MACHINE FROM POWER PLANT / CYPRUS – 2015 :

Transfer to another country, of the generator, which was determined to have failure within the power plant, and transfer and reassembly of the related machine in the former power plant after repair.

ENGINE CRANKSHAFT CHANGING / TURKEY-2016:

Damaged crankshaft were changed (disassembled – assembled) with the new one by 11 Industrial as a service & repairment task.

POWER PLANT RELOCATION PROJECT (20 MW)/ TURKEY-2016:

All main machine groups, electronic and mechanical equipment were disassembled by 11 Industrial and they were transported and reassembled to the new jobsite.
Additionally, engine hall new steel construction were manufactured and assembled by 11 Industrial.

PROJECT OF REPLACE OF ALTERNATOR WITH NEW GENERATION / TURKEY – 2017:

New generation alternator was transported and replaced the old one by 11 Industrial.

INSTALLATION OF POWER STORAGE SYSTEM FOR NATURAL GAS POWER PLANT / HUNGARY – 2018:

Power storage system equipments were transported, mounted and connected the system of power plant by 11 Industrial.